Work schedule for Marriotts Close, WitneyBelow is the expected timeline of the development: January 2008 February 2008 March 2008 April 2008 Steel work complete on multi screen cinema Commencement of external shell Retail units 1-6 steel work commences for a period of six weeks Steel work continues to construct the multi-storey car park with shell works to follow June 2008 Summer 2008 Autumn / Winter 2008 Spring 2009 Summer 2009 Autumn 2009 |